We provide independent, impartial advice, with internal components incorporated being of the clients choosing.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
General Information | |||
Traditional Build | GPR Pod | Taplanes Pod | |
Product Cost | £3,000 | £2,800 | £4,752 |
Mould Set Up Cost | 0 | £30,000 | 0 |
Minimum Order Quantity (Units) | 1 | 200 | 1 |
Per unit cost (Including Overhead) | £3,000 | £2,950 | £4,752 |
Installation Cost | |||
Man Days require for Installation | 6 | 4 | 1 |
Average UK Man Day Cost | £280 | £280 | £280 |
Crane Cost Per Day | 0 | £400 | 0 |
Total Installation Cost | £1,680 | £1,520 | £280 |
Initial Investment (1st Installation) | £4,680 | £4,470 | £5,032 |
Shelf Life (Years) | 10 | 8 | 30 |
Dismantling Cost (If the product fail or needs redesign) | |||
Man Days require for Dismantling | 6 | 6 | 1 |
Average UK Man Day Cost | £280 | £280 | £280 |
Total Dismantling Cost | £1,680 | £1,680 | £280 |
Recyclability | No | No | Yes |
Waste Disposal Fee | £100 | £100 | £ – |
Total Dismantling Cost | £1,780 | £1,780 | £280 |
Assuming the bathroom facilities expected to be in function for 20 Years | ||||
10 Years Refurbishment (Assuming 20% increment in 10 years) | Traditional Build | GPR Pod | Taplanes Pod | |
Dismantling Cost (If the product fail or needs redesign) | ||||
Man Days require for Dismentaling | 6 | 6 | ||
Average UK Man Day Cost | £336 | £336 | ||
Total Dismantling Cost | £2,016 | £2,016 | ||
Recyclability | No | No | ||
Waste Disposal Fee | £120 | £120 | ||
Total Dismantling Cost | £2,136 | £2,136 | ||
Brand New Purchase | ||||
Product Cost (New Cost) | £3,600 | £3,540 | ||
Mould Set Up Cost | 0 | £ – | ||
Minimum Order Quantity (Units) | 1 | 1 | ||
Per unit cost (Including Overhead) | £3,600 | £3,540 | ||
New Installation Cost | ||||
Man Days require for Installation | 6 | 4 | ||
Average UK Man Day Cost | £336 | £336 | ||
Crane Cost Per Day | 0 | £ 480 | ||
Total Installation Cost | £2,016 | £ 1,824 |
20 Year Refurbishment – Assume 20% increment in 11th to 20th Years | Traditional Build | GPR Pod | Taplanes Pod |
Dismantling Cost (If the product fail or needs redesign) | |||
Man Days require for Dismantling | 6 | 6 | |
Average UK Man Day Cost | £403 | £403 | |
Total Dismantling Cost | £2,419 | £2,419 | |
Recyclability | No | No | |
Waste Disposal Fee | £144 | £144 | |
Total Dismantling Cost | £2,563 | £2,563 | |
Brand New Purchase | |||
Product Cost | £4,320 | £4,248 | |
Mould Set Up Cost | 0 | £ – | |
Minimum Order Quantity (Units) | 1 | 1 | |
Per unit cost (Including Overhead) | £4,320 | £4,248 | |
New Installation Cost | |||
Man Days require for Installation | 6 | 4 | |
Average UK Man Day Cost | £403 | £403 | |
Crane Cost Per Day | 0 | £480 | |
Total Installation Cost | £2,419 | £2,093 | |
Unit cost + Install cost (total cost) | £6,739 | £6,341 |
Total Investment for having a fully function bathroom facilities | |||
Traditional | GRP | Taplanes | |
Shelf Life | 10 | 8 | 30 |
Initial Investment + Installation | £4,680 | £4,470 | £5,032 |
10 Years Refurbishment Cost | £7,752 | £7,500 | |
20 Years Refurbishment Cost | £9,302 | £8,904 | |
Total Investment on Bathroom Facilities (Over 20 Years) | £21,734 | £20,874 | £5,032 |
Cost per year for having a fully function bathroom facilities | £1,087 | £1,044 | £252 |
332% | 315% |